Improvement of Operating Efficiency on Advanced Wastewater Plant Using Statistical Approach
暂无分享,去创建一个
Statistical analysis technique was applied to operating parameters and removal efficiency data sets obtained from advanced wastewater treatment plant during 1 year. Through factor analysis three factors derived varimax rotation were selected each plant. Three components explained 96%, 87% of the total variance of the process, respectively. The components on Plant were identified in the following order : 1) Shortening the SRT during high-flow period, 2) Keeping biomass high on winter 3) factor was related to DO. On DNR plant, we defined them as follows: factor 1, Prolonged the SRT during high-flow period; factor 2 was related to sludge return; factor 3, Influent BOD during low-DO period. This technique was believed to assist operators in identifying priorities to improve operation efficiency.