An approach for identifying the most likely activity sequence in a resource-constrained stochastic network
暂无分享,去创建一个
[1] Sergey Bushuyev,et al. Entropy measurement as a project control tool , 1999 .
[2] Bruce M. Woodworth,et al. Identifying the critical sequence in a resource constrained project , 1988 .
[3] Avraham Shtub,et al. Project management: engineering, technology, and implementation , 1994 .
[4] John Bowers,et al. Criticality in Resource Constrained Networks , 1995 .
[5] Lee W. Schruben,et al. Simulation modeling with event graphs , 1983, CACM.
[6] Ricki G. Ingalls,et al. PERT Scheduling with Resource Constraints Using Qualitative Simulation Graphs , 2004 .
[7] Giovanni Mummolo. Measuring uncertainty and criticality in network planning by PERT-path technique , 1997 .
[8] Vidyadhar G. Kulkarni,et al. A classified bibliography of research on stochastic PERT networks: 1966-1987 , 1989 .
[9] Pierpaolo Pontrandolfo,et al. Project duration in stochastic networks by the PERT-path technique , 2000 .
[10] Jerome D. Wiest. Some Properties of Schedules for Large Projects with Limited Resources , 1964 .
[11] J. Bowers. Identifying critical activities in stochastic resource constrained networks , 1996 .
[12] Terry Williams. Criticality in Stochastic Networks , 1992 .
[13] Bajis M. Dodin,et al. Approximating the Criticality Indices of the Activities in PERT Networks , 1985 .
[14] Andrew B. Whinston,et al. The implementation of temporal intervals in qualitative simulation graphs , 2000, TOMC.
[15] Robert L. Armacost,et al. Understanding Simulation Solutions to Resource Constrained Project Scheduling Problems with Stochastic Task Durations , 1998 .
[16] Giovanni Mummolo. PERT-path network technique: a new approach to project planning , 1994 .