SPEAR 3 upgrade project: a status report

The SPEAR 3 upgrade project at SSRL will replace the original FODO lattice with a 234-m, 18-cell DBA lattice with gradient dipoles. The new hardware draws heavily on PEP-II B-Factory technology: a copper vacuum chamber, IGBT power supply technology, and mode-damped rf cavities to reach beam currents up to 500 mA at 3 GeV. First article magnets, supports, girders, vacuum chambers, pumps and RF components have been fabricated and a prototype girder assembly is nearing completion. I&C systems, radiation shielding and utility upgrades are in progress. In this paper we report on the status of the main accelerator subsystems.

[1]  K. Wille,et al.  A Slotted pipe kicker for high current storage rings , 1994 .

[2]  Yuri Nosochkov,et al.  Study of low /spl beta//sub y/ straight section in SPEAR 3 , 2001, PACS2001. Proceedings of the 2001 Particle Accelerator Conference (Cat. No.01CH37268).

[3]  R.L. Cassel,et al.  A solid state induction modulator for SLAC NLC , 1999, Proceedings of the 1999 Particle Accelerator Conference (Cat. No.99CH36366).

[4]  W. Ross,et al.  Commissioning experience with the PEP-II low-level RF system , 1997, Proceedings of the 1997 Particle Accelerator Conference (Cat. No.97CH36167).

[5]  Robert Hettel Design of the SPEAR 3 Light Source , 2003 .

[6]  H. Schwarz,et al.  Development of a high-power RF cavity for the PEP-II B factory , 1995, Proceedings Particle Accelerator Conference.

[7]  Robert Hettel SPEAR 3 Design Report , 2002 .

[8]  L. Sapozhnikov,et al.  Low level RF system design for the PEP-II B factory , 1994, Proceedings Particle Accelerator Conference.