Three DTL tanks and 32 SDTL tanks for the Japan Proton Accelerator Research Complex (J-PARC) were assembled at KEK site. After the assembling, the highpower conditioning of the DTL1 and 12 SDTL tanks and the beam acceleration test for the DTL1 ware carried out [1, 2]. And then all the DTL and SDTL tanks have to be transported form KEK to JAEA. In order to confirm the effect of the transportation to the drift tube alignment, we measured the displacement of the drift tube positions before and after the transportation by using a prototype cavity. As a result of the test, the measured displacement of the drift tubes by the transportation was less than 0.02mm which is consestent in the measurement accuracy. Based on this result, all the DTL and SDTL tanks were transported form KEK to JAEA. In this paper, the transportation results of the prototype cavity and the DTL/SDTL tanks are described.