An Algorithm for Hoisting Time Calculation in Super-tall Building Construction
暂无分享,去创建一个
An installation of the construction lift has a few limitations by many constrains and these have influences on labor productivity, that can be changed by vertical-transportation management. In the super-tall building construction, a management of construction lift operation is one of the most important factor, but existing methodologies depend on skilled practitioners` experiences. And it is true that the expertise resulted by the experiences does not transfer to the next generation. This study is a part of lifting-management simulation development which aims at the optimal construction lift management. A proposed algorithm is focus on lifting time calculation considering an acceleration capability. This research evaluates the result accuracy using comparative analysis on simulation result and field measuring time.