Integration of Scheduling and Control with Closed Loop Implementation

We propose a closed loop strategy to implement simultaneous scheduling and control for chemical processes subject to disturbances. Evidences from published work in the literature suggest that the integration of scheduling and control for multiproduct processes results in optimal production taking into consideration transition stages. On the basis of that, we build a closed loop implementation for simultaneous scheduling and control, which mitigates the effects of disturbances by generating new solutions once the state deviation due to disturbances is detected. To test the performance of the proposed methodology, we use two case studies, and compare their performance with that of open loop implementation. The results of the case studies verify the effectiveness of closed loop strategy in dealing with process disturbances.

[1]  Ignacio E. Grossmann,et al.  Simultaneous Cyclic Scheduling and Control of a Multiproduct CSTR Reactor , 2006 .

[2]  Christoph W. Ueberhuber,et al.  Stability Properties of Implicit Runge–Kutta Methods , 1985 .

[3]  Marianthi G. Ierapetritou,et al.  Process scheduling under uncertainty: Review and challenges , 2008, Comput. Chem. Eng..

[4]  Ravindra D. Gudi,et al.  Optimal Grade Transition in Polymerization Reactors: A Comparative Case Study† , 2006 .

[5]  Marianthi G. Ierapetritou,et al.  Reactive scheduling using parametric programming , 2008 .

[6]  Riccardo Scattolini,et al.  Robustness of receding horizon control for nonlinear discrete-time systems , 1998, Robustness in Identification and Control.

[7]  Rüdiger Franke,et al.  Production campaign planning including grade transition sequencing and dynamic optimization , 2005, Comput. Chem. Eng..

[8]  Iiro Harjunkoski,et al.  Production optimization for continuously operated processes with optimal operation and scheduling of multiple units , 2006, Comput. Chem. Eng..

[9]  L. Biegler,et al.  A robust and efficient mixed-integer non-linear dynamic optimization approach for simultaneous design and control , 2005 .

[10]  Francis J. Doyle,et al.  Control‐relevant scheduling of polymer grade transitions , 2002 .

[11]  Marianthi G. Ierapetritou,et al.  Robust optimization for process scheduling under uncertainty , 2008 .

[12]  Francis J. Doyle,et al.  Hybrid approach to polymer grade transition control , 2004 .

[13]  Iiro Harjunkoski,et al.  Integration of scheduling and control - Theory or practice? , 2009, Comput. Chem. Eng..

[14]  F. You,et al.  INTEGRATION OF SCHEDULING AND CONTROLLER DESIGN FOR A MULTIPRODUCT CSTR , 2011 .

[15]  Elisabet Capón-García,et al.  Costs for rescheduling actions: a critical issue for reducing the gap between scheduling theory and practice , 2008 .

[16]  Ignacio E. Grossmann,et al.  Simultaneous scheduling and control of multiproduct continuous parallel lines , 2010 .

[17]  Rajagopalan Srinivasan,et al.  A model-based rescheduling framework for managing abnormal supply chain events , 2007, Comput. Chem. Eng..

[18]  Kishalay Mitra,et al.  Resiliency Issues in Integration of Scheduling and Control , 2010 .

[19]  Ignacio E. Grossmann,et al.  Simultaneous Cyclic Scheduling and Control of Tubular Reactors: Parallel Production Lines , 2010 .

[20]  I. Grossmann Simultaneous Cyclic Scheduling and Control of Tubular Reactors: Single Production Lines , 2010 .

[21]  Ignacio E. Grossmann,et al.  Simultaneous cyclic scheduling and optimal control of polymerization reactors , 2007 .

[22]  M. Ierapetritou,et al.  SIMULTANEOUS SCHEDULING AND CONTROL WITH CLOSED LOOP IMPLEMENTATION ON PARALLEL UNITS , 2011 .

[23]  David Q. Mayne,et al.  Constrained model predictive control: Stability and optimality , 2000, Autom..

[24]  Gabriela P. Henning,et al.  Computers and Chemical Engineering , 2022 .

[25]  Ignacio E. Grossmann,et al.  Simultaneous design, scheduling, and optimal control of a methyl-methacrylate continuous polymerization reactor , 2008 .

[26]  Ignacio E. Grossmann,et al.  Lagrangean heuristic for the scheduling and control of polymerization reactors , 2008 .

[27]  Rajagopalan Srinivasan,et al.  Heuristic rescheduling of crude oil operations to manage abnormal supply chain events , 2007 .

[28]  Efstratios N. Pistikopoulos,et al.  Perspectives in Multiparametric Programming and Explicit Model Predictive Control , 2009 .

[29]  Paul I. Barton,et al.  Mixed-integer dynamic optimization I: problem formulation , 1999 .