An algorithm for optimal cyclic scheduling in a robotic cell with flexible processing times

This paper describes an exact algorithm for the optimal cyclic scheduling in a robotic cell with flexible processing times and a material handling robot. The problem is formulated with the prohibited intervals of the cycle time based on the capacity constraints of the machines and the robot. After the analysis of the developed mathematic model, the problem is transformed to enumerate the non-prohibited intervals for the cycle time. An efficient branch and bound algorithm is proposed to complete this enumeration procedure. Computational results on randomly generated test instances indicate that the algorithm is effective.

[1]  L. Lei,et al.  DETERMINING OPTIMAL CYCLIC HOIST SCHEDULES IN A SINGLE-HOIST ELECTROPLATING LINE , 1994 .

[2]  Chengbin Chu,et al.  A polynomial algorithm for 2-degree cyclic robot scheduling , 2003, Eur. J. Oper. Res..

[3]  H. Neil Geismar,et al.  Sequencing and Scheduling in Robotic Cells: Recent Developments , 2005, J. Sched..

[4]  L. W. Phillips,et al.  Mathematical Programming Solution of a Hoist Scheduling Program , 1976 .

[5]  A. Che,et al.  Single-track multi-hoist scheduling problem: a collision-free resolution based on a branch-and-bound approach , 2004 .

[6]  Chengbin Chu,et al.  Cyclic hoist scheduling in large real-life electroplating lines , 2007, OR Spectr..

[7]  W. Ng A branch and bound algorithm for hoist scheduling of a circuit board production line , 1996 .

[8]  Chengbin Chu A faster polynomial algorithm for 2-cyclic robotic scheduling , 2006, J. Sched..

[9]  Eugene Levner,et al.  Multiple-part cyclic hoist scheduling using a sieve method , 1999, IEEE Trans. Robotics Autom..

[10]  Christian Bierwirth,et al.  A heuristic scheduling procedure for multi-item hoist production lines , 2007 .

[11]  Feng Chu,et al.  Multicyclic hoist scheduling with constant processing times , 2002, IEEE Trans. Robotics Autom..

[12]  Lei Lei,et al.  The minimum common-cycle algorithm for cyclic scheduling of two material handling hoists with time window constraints , 1991 .

[13]  Vadim E. Levit,et al.  An improved algorithm for cyclic flowshop scheduling in a robotic cell , 1997 .

[14]  Chengbin Chu,et al.  Cyclic scheduling of a hoist with time window constraints , 1998, IEEE Trans. Robotics Autom..

[15]  Chengbin Chu,et al.  Cyclic multiple-robot scheduling with time-window constraints using a critical path approach , 2007, Eur. J. Oper. Res..

[16]  Henry L. W. Nuttle,et al.  Hoist Scheduling For A PCB Electroplating Facility , 1988 .

[17]  Lei Lei,et al.  Optimal Cyclic Scheduling Of A Robotic Processing Line With Two-Product And Time-Window Constraints , 2001 .