Steady-state operating conditions of very long EHVAC cable lines: Two case studies

Abstract The paper deals with the operation of very long EHV AC cable lines in a well-developed bulk power system, by simulating two 400 kV–50 Hz single circuit cable lines, 80–100 km long, installed at different locations of the Italian transmission network, both standing alone and in parallel to an existing overhead line. The power transmission limits of the considered cable lines are assessed analytically, as well as the required amount of shunt compensation and its location, at line terminals or also at mid-line; a criterion for sizing mid-line shunt compensation is also proposed. In order to check theoretical analyses carried out by analytical formulas, AC load flow simulations of the transmission network with the hypothetical cable lines in place are evaluated, referring to severe loading conditions in both normal and post-contingency operation. Open-ended cable operation and shunt compensation contingencies are also addressed. Results show that power transmission limits due to cable ampacity and higher active power flows due to low cable reactance do not pose special constraints on the operation of the powerful network under examination. Appropriate shunt compensation minimizes the effects of surplus cable reactive power, allowing to operate long 400 kV–50 Hz cable lines (up to 100 km at least) with reactors at line terminals only. Moreover, if shunt compensation is installed also at mid-line, operating capabilities of the long cable lines are enhanced and losses reduced.

[1]  C. Genesi,et al.  Power flow based indices for the coordination of transmission and generation system planning , 2009, 2009 IEEE Bucharest PowerTech.

[2]  S. Lauria,et al.  Shunt compensation of EHV Cables and Mixed Overhead-Cable Lines , 2007, 2007 IEEE Lausanne Power Tech.

[3]  Roberto Benato,et al.  EHV AC Undergrounding Electrical Power: Performance and Planning , 2010 .

[4]  Roberto Benato,et al.  Operating capability of long AC EHV transmission cables , 2005 .

[5]  C. S. Schifreen,et al.  Charging Current Limitations in Operation or High-Voltage Cable Lines [includes discussion] , 1956, Transactions of the American Institute of Electrical Engineers Part III Power Apparatus and Systems.

[6]  L. Colla,et al.  Dimensionamento della compensazione derivata nelle linee AAT “miste” cavo-aerea , 2006 .

[7]  F.M. Gatta,et al.  Very long EHV cables and mixed overhead-cable lines. Steady-state operation , 2005, 2005 IEEE Russia Power Tech.

[8]  Stefano Lauria,et al.  Improving high-voltage transmission system adequacy under contingency by genetic algorithms , 2009 .

[9]  J. J. Dougherty,et al.  Long Cable Lines-Alternating Current with Reactor Compensation or Direct Current , 1962, Transactions of the American Institute of Electrical Engineers. Part III: Power Apparatus and Systems.

[10]  Alberto Geri,et al.  Steady-state operating conditions of very long EHVAC cable lines , 2011 .

[11]  F. M. Gatta,et al.  Power system adequacy: An efficient procedure based on genetic algorithms , 2009, 2009 IEEE Bucharest PowerTech.

[12]  S. Lauria,et al.  Steady-state operation of very long EHV AC cable lines , 2009, 2009 IEEE Bucharest PowerTech.