Testing the Value of 4D Visualizations for Enhancing Mindfulness in Utility Reconstruction Works

AbstractThis paper reports on an ethnographic-action research study of four-dimensional (4D) based coordination in three utility reconstruction projects. This research shows that implementation of 4D models in planning meetings supports mindful behavior, making stakeholders: (1) sensitive to operational processes, (2) pre-occupied with errors and inaccuracies, (3) resistant to simplifying construction plans, and (4) resilient and aware of process alternatives. By being first in synthesizing 4D implementation and mindfulness literature, this study makes a step toward a more systematic and comprehensive analysis of the impact of 4D on coordination. This study provides a practical contribution by showing that stakeholders in utility projects can use 4D to better anticipate and contain unwanted situations. This helps them tackling coordination issues effectively, and may eventually reduce the overruns and rework in utility construction.

[1]  Stuart D. Anderson,et al.  Empirical Study on the Merit of Web-Based 4D Visualization in Collaborative Construction Planning and Scheduling , 2007 .

[2]  Rogier Jongeling,et al.  A method for planning of work-flow by combined use of location-based scheduling and 4D CAD , 2007 .

[3]  Jian-Ping Zhang,et al.  4D Dynamic Management for Construction Planning and Resource Utilization , 2004 .

[4]  Willemijn Dicke,et al.  “Soft” Public Values in Jeopardy: Reflecting on the Institutionally Fragmented Situation in Utility Sectors , 2009 .

[5]  Jennifer Whyte,et al.  Managing digital coordination of design: emerging hybrid practices in an institutionalized project setting , 2011 .

[6]  Michael J. Horman,et al.  Ethnographic Theory-Building Research in Construction , 2010 .

[7]  Timo Hartmann,et al.  Implementing information systems with project teams using ethnographic-action research , 2009, Adv. Eng. Informatics.

[8]  David Heesom,et al.  Trends of 4D CAD applications for construction planning , 2004 .

[9]  K. Weick,et al.  Collective mind in organizations: Heedful interrelating on flight decks. , 1993 .

[10]  Kathleen M. Sutcliffe,et al.  Mindfulness and the Quality of Organizational Attention , 2006, Organ. Sci..

[11]  Wei-Chih Wang,et al.  Integrating building information models with construction process simulations for project scheduling support , 2014 .

[12]  Gilles Halin,et al.  Designing adapted visualization for collaborative 4D applications , 2013 .

[13]  K. Roberts,et al.  Must accidents happen? Lessons from high-reliability organizations , 2001 .

[14]  Sheryl Staub-French,et al.  Visualizing high-rise building construction strategies using linear scheduling and 4D CAD , 2009 .

[15]  Lieyun Ding,et al.  Application of 4D visualization technology for safety management in metro construction , 2013 .

[16]  John Smallwood,et al.  THE POTENTIAL OF 4D CAD AS A TOOL FOR CONSTRUCTION MANAGEMENT , 2004 .

[17]  Timo Hartmann,et al.  4D CAD models to support the coordination of construction activities between contractors , 2015 .

[18]  Andrew Davies,et al.  From hero to hubris – Reconsidering the project management of Heathrow’s Terminal 5 , 2010 .

[19]  Martin Fischer,et al.  Supporting the constructability review with 3D/4D models , 2007 .

[20]  Zhen-Zhong Hu,et al.  BIM- and 4D-based integrated solution of analysis and management for conflicts and structural safety problems during construction: 2. Development and site trials , 2011 .

[21]  James Casler,et al.  Revisiting NASA as a High Reliability Organization , 2014 .

[22]  Timo Hartmann,et al.  Comparing mindfulness in manual and 4D supported coordination practices , 2014 .

[23]  Timo Hartmann,et al.  4D CAD Based Method for Supporting Coordination of Urban Subsurface Utility Projects , 2016 .

[24]  Timothy J. Vogus,et al.  The Safety Organizing Scale: Development and Validation of a Behavioral Measure of Safety Culture in Hospital Nursing Units , 2007, Medical care.

[25]  M. V. Eeten,et al.  Systems that Should Have Failed: Critical Infrastructure Protection in an Institutionally Fragmented Environment , 2007 .

[26]  Rahul Kashyap,et al.  An evaluation of the applicability of 4D CAD on construction projects , 2010 .

[27]  Saad H.S. Al-Jibouri,et al.  Using 4D CAD to visualize the impacts of highway construction on the public , 2013 .

[28]  Timothy J. Vogus,et al.  Organizational Mindfulness and Mindful Organizing: A Reconciliation and Path Forward , 2012 .

[29]  Meng-Han Tsai,et al.  A framework of information visualization for multi-system construction , 2011 .

[30]  Meng-Han Tsai,et al.  A three-stage framework for introducing a 4D tool in large consulting firms , 2010, Adv. Eng. Informatics.

[31]  K. Sutcliffe,et al.  Overcoming dysfunctional momentum: Organizational safety as a social achievement , 2009 .

[32]  André G. Dorée,et al.  High reliability organizing at the boundary of the CM domain , 2014 .

[33]  Hanbin Luo,et al.  A BIM-based construction quality management model and its applications , 2014 .

[34]  Robert G. Eccles,et al.  Bureaucratic versus Craft Administration: The Relationship of Market Structure to the Construction Firm. , 1981 .

[35]  R. Sternberg Images of Mindfulness , 2000 .

[36]  Panagiotis Mitropoulos,et al.  Safety as an Emergent Property: Investigation into the Work Practices of High-Reliability Framing Crews , 2009 .

[37]  Martin Fischer,et al.  Areas of Application for 3D and 4D Models on Construction Projects , 2008 .

[38]  Hyunjoo Kim,et al.  Generating construction schedules through automatic data extraction using open BIM (building information modeling) technology , 2013 .

[39]  Claude Villiers,et al.  Productivity in Daytime and Nighttime Construction of Urban Sewer Systems , 2014 .

[40]  Hyoun-Seok Moon,et al.  Development of a 4D object-based system for visualizing the risk information of construction projects , 2013 .