한국형 경량전철 다중편성시험방안

LRT System Application Project is performed for the purpose of technical advancement and stabilization of K-AGT system from the viewpoint of practical use and commercialization. For those purpose, the performance test and evaluation procedure for signaling system have been developed, including the scheme of verifying the performance and function of signaling system under driverless multiple train operation environment. In this paper, multiple train operation scheme in K-AGT test line is presented. Test schemes for maintaining the safety distance between trains, operation scenario considering shunting and turning of train, and dia operation schemes in test line are reviewed while researching test vehicle features, route condition and running pattern. Additional equipments for testing each scheme are also reviewed.