Pipe Transmission Project Planning Using What If Analysis Method

In order to succeed Indonesia’s mission to provide 23.000 MegaWatt, the gas pipeline transmission has been built. The Project consists of many activities that related to each other, If one of the activities are having a problem that caused a delay, then the succeeding activities will get affected and could cause a project’s delay. To anticipate, it needs the acceleration of the project’s activity. In this case, the pipe transmission project would cause a 7 day delay. To accelerate it, this study gives the calculation, using “What If Analysis Method” on “Critical Path Method”. The acceleration actions are treated in accordance with providing extra working hours and the certain amount of manpower in the succeeding activities.