Key Success Indicators for PPP Projects: Evidence from Hong Kong

Because a consensus has yet to be reached on how to assess the success of a Public-Private Partnership (PPP) project, it is meaningful to study the multidimensional indicators to assess PPP project success. It merits attention that PPP project success indicators are totally different from PPP critical success factors (CSFs), which have attracted a lot of attention from scholars. This study conducts a questionnaire survey to identify the crucial considerations of project success from the perspectives of different PPP stakeholders. In line with previous studies, five dimensions of PPP project success that were developed from different stakeholder viewpoints and time frameworks were tested based on the empirical data. The dimensions mapped in the study not only provide a benchmark for practitioners to diagnose the extent of PPP project success but also provide a solid foundation for scholars to conduct further studies regarding PPP project success.

[1]  G. G. Stokes "J." , 1890, The New Yale Book of Quotations.

[2]  H. Kaiser An index of factorial simplicity , 1974 .

[3]  Jeffrey K. Pinto,et al.  Critical factors in successful project implementation , 1987, IEEE Transactions on Engineering Management.

[4]  Peter W. G. Morris,et al.  The Anatomy of Major Projects: A Study of the Reality of Project Management , 1988 .

[5]  B. Price A First Course in Factor Analysis , 1993 .

[6]  Aaron J. Shenhar,et al.  The Role of Contract Type in the Success of R&D Defense Projects under Increasing Uncertainty , 2000 .

[7]  Thomas de Quincey [C] , 2000, The Works of Thomas De Quincey, Vol. 1: Writings, 1799–1820.

[8]  A. Shenhar,et al.  Project Success: A Multidimensional Strategic Concept , 2001 .

[9]  Aaron J. Shenhar,et al.  Refining the search for project success factors: a multivariate, typological approach , 2002 .

[10]  장윤희,et al.  Y. , 2003, Industrial and Labor Relations Terms.

[11]  Tzvi Raz,et al.  An empirical analysis of the relationship between project planning and project success , 2003 .

[12]  E. Westerveld,et al.  The Project Excellence Model®: linking success criteria and critical success factors , 2003 .

[13]  R. Gonzalez Applied Multivariate Statistics for the Social Sciences , 2003 .

[14]  John L.P. Thompson,et al.  Missing data , 2004, Amyotrophic lateral sclerosis and other motor neuron disorders : official publication of the World Federation of Neurology, Research Group on Motor Neuron Diseases.

[15]  Adam Collins,et al.  PROJECT SUCCESS — A SURVEY , 2004 .

[16]  A. Akintoye,et al.  PERFORMANCE INDICATORS FOR SUCCESSFUL CONSTRUCTION PROJECT PERFORMANCE , 2005 .

[17]  A. Akintoye,et al.  Perceptions of positive and negative factors influencing the attractiveness of PPP/PFI procurement for construction projects in the UK: Findings from a questionnaire survey , 2005 .

[18]  Jason W. Osborne,et al.  Best practices in exploratory factor analysis: four recommendations for getting the most from your analysis. , 2005 .

[19]  Xueqing Zhang Public Clients' Best Value Perspectives of Public Private Partnerships in Infrastructure Development , 2006 .

[20]  N. El-Gohary,et al.  Stakeholder management for public private partnerships , 2006 .

[21]  K Nogeste,et al.  Performance measures and project procurement , 2007 .

[22]  M. Loosemore,et al.  Risk allocation in the private provision of public infrastructure , 2007 .

[23]  Leonard D. Stern,et al.  A Visual Approach to SPSS for Windows: A Guide to SPSS 17.0 , 2007 .

[24]  Tahir M. Nisar,et al.  Risk Management in Public–Private Partnership Contracts , 2007 .

[25]  Ezekiel Chinyio,et al.  A Framework for the Risk Management of Private Finance Initiative Projects , 2008 .

[26]  Qiming Li,et al.  Selection of performance objectives and key performance indicators in public–private partnership projects to achieve value for money , 2009 .

[27]  Michael J. Garvin,et al.  Procurement Systems: A Cross‐Industry Project Management Perspective , 2009 .

[28]  Qiming Li,et al.  Performance Objectives Selection Model in Public-Private Partnership Projects Based on the Perspective of Stakeholders , 2010 .

[29]  P. Lam,et al.  Critical Success Factors for PPPs in Infrastructure Developments: Chinese Perspective , 2010 .

[30]  B. Hwang,et al.  Public private partnership projects in Singapore factors, critical risks and preferred risk allocation from the perspective of contractors / , 2013 .

[31]  Bon-Gang Hwang,et al.  Critical success factors for enterprise risk management in Chinese construction companies , 2013 .

[32]  Xianbo Zhao,et al.  Project System Vulnerability to Political Risks in International Construction Projects: The Case of Chinese Contractors , 2014 .

[33]  Bon-Gang Hwang,et al.  Influence of Trade-Level Coordination Problems on Project Productivity , 2014 .

[34]  Jason W. Osborne,et al.  Best Practices in Exploratory Factor Analysis , 2014 .

[35]  이화영 X , 1960, Chinese Plants Names Index 2000-2009.

[36]  Ming Shan,et al.  Investigating the Effectiveness of Response Strategies for Vulnerabilities to Corruption in the Chinese Public Construction Sector , 2014, Science and Engineering Ethics.

[37]  Bon-Gang Hwang,et al.  Value Management in Singaporean Building Projects: Implementation Status, Critical Success Factors, and Risk Factors , 2015 .

[38]  Xianbo Zhao,et al.  Agent-Based Debt Terms' Bargaining Model to Improve Negotiation Inefficiency in PPP Projects , 2016, J. Comput. Civ. Eng..

[39]  Xianbo Zhao,et al.  Modelling paths of risks associated with BIM implementation in architectural, engineering and construction projects , 2017 .

[40]  Gorjan Alagic,et al.  #p , 2019, Quantum information & computation.

[41]  Xianbo Zhao,et al.  Ex Post Risk Management in Public-Private Partnership Infrastructure Projects , 2017 .

[42]  Dong Zhao,et al.  Risk-Compensation Behaviors on Construction Sites: Demographic and Psychological Determinants , 2017 .

[43]  Xianbo Zhao,et al.  Investigating the relationship between communication-conflict interaction and project success among construction project teams , 2017 .

[44]  Xianbo Zhao,et al.  Exploring the Factors Inducing Contractors’ Unethical Behavior: Case of China , 2017 .

[45]  R. Sarpong,et al.  Bio-inspired synthesis of xishacorenes A, B, and C, and a new congener from fuscol† †Electronic supplementary information (ESI) available. See DOI: 10.1039/c9sc02572c , 2019, Chemical science.

[46]  Information Asymmetry in Renegotiation of Public–Private Partnership Projects , 2018, Journal of Computing in Civil Engineering.

[47]  W. Hager,et al.  and s , 2019, Shallow Water Hydraulics.

[48]  Tsuyoshi Murata,et al.  {m , 1934, ACML.