초고층 커튼월 공정관리 최적화를 위한 건설성능 데이터 표준화

High-rise building construction has been increasing for the recent years and the construction process has become more complicated. This suggests a need for precise planning based on reliable data to prevent cost overruns and delays. However, the process planning is implemented based mainly on the experience of engineers that can result in critical damage in cost and time. Accurate productivity estimation and unit cost analysis must be considered important matter to prevent such disaster. This study estimates productivity and unit cost of curtain wall operations in high-rise building construction by simulation techniques and statistical methodologies. This study suggests a decision making methodology for the site personnel that enables to compare various combinations of productivity and unit cost based on reliable data that has been collected in actual construction sites. It is expected that this study contributes to the following research of developing an optimized construction performance assembling model for the site personnel.