The Information-Related Time Loss on Construction Sites: A Case Study on Two Sites

Information management is essential in construction projects. Existing research has identified and discussed problems in communication and information transfer among different stakeholders, such as the loss of information caused by fragmentation and information islands. However, there are few statistics about the direct time waste caused by information loss arising from poor communication and information management. Existing surveys relying on self-reporting questionnaires and interviews often contain various biases. This paper presents a direct observation of two construction sites in China in relation to wasted time and the information flows in these time-wasting events. Analysis of the observation data provides objective and comprehensive statistics on time wasted due to inconsistent information, dislocation and ambiguity. This research also analyses the correlation between participants, information carriers, information loss and the amount of time wasted. Finally, the wasting of time is analysed from the perspective of information flows and problems that cannot be addressed by information technologies are discussed.

[1]  Christine Pasquire,et al.  The 8th flow - common understanding , 2012 .

[2]  Laura Johnson,et al.  How Many Interviews Are Enough? , 2006 .

[3]  Mark R Lehto,et al.  Computerized coding of injury narrative data from the National Health Interview Survey. , 2004, Accident; analysis and prevention.

[4]  A. Nederhof Methods of coping with social desirability bias: A review. , 1985 .

[5]  Rafael Sacks,et al.  An Empirical Study of Information Flows in Multidisciplinary Civil Engineering Design Teams using Lean Measures , 2011 .

[6]  Andrew R.J. Dainty,et al.  Review of construction safety research methods: integrating theory and practice , 2011 .

[7]  Rafael Sacks,et al.  Measuring information flow in the detailed design of construction projects , 2010 .

[8]  Yasemin Nielsen,et al.  WEB-BASED INFORMATION FLOW MODELLING IN CONSTRUCTION , 2001 .

[9]  B Hobbs,et al.  Development of automated communication of system for managing site information using internet technology , 2002 .

[10]  Roger Lundegård Information Management in Construction Projects: Current Practices and Guidelines , 1998 .

[11]  Robert Amor,et al.  Information Technology for Construction: Recent Work and Future Directions , 2002, J. Inf. Technol. Constr..

[12]  Aj Marshall-Ponting,et al.  An nD modelling approach to improve communication processes for construction , 2005 .

[13]  Raymond E. Levitt,et al.  Computer Integration: Reducing Fragmentation in AEC Industry , 1989 .

[14]  Herman Glenn Ballard,et al.  THE LAST PLANNER SYSTEM OF PRODUCTION CONTROL , 2000 .

[15]  van de Mortel,et al.  Faking it: Social desirability response bias in self-report research , 2008 .

[16]  P. Keats,et al.  Multiple text analysis in narrative research: visual, written, and spoken stories of experience , 2009 .

[17]  Ming-Kuan Tsai,et al.  Improving communication barriers for on-site information flow: An exploratory study , 2009, Adv. Eng. Informatics.

[18]  Lauri Koskela,et al.  An exploration towards a production theory and its application to construction , 2000 .

[19]  Kasun Hewage,et al.  A novel solution for construction on-site communication – the information booth , 2009 .

[20]  M. Hewstone,et al.  Introduction to Social Psychology, third ed. , 2002 .

[21]  Bryan Cleal,et al.  Hazard scenarios of truck drivers' occupational accidents on and around trucks during loading and unloading. , 2010, Accident; analysis and prevention.

[22]  Thomas Froese,et al.  The impact of emerging information technology on project management for construction , 2010 .

[23]  Michael A. Hogg,et al.  Introduction to Social Psychology , 2002 .

[24]  Kenneth T. Sullivan,et al.  How To Measure the Benefits of BIM - A Case Study Approach , 2012 .

[25]  W. Mcdougall An introduction to social psychology , 1909 .

[26]  Xiaolong Xue,et al.  IT supported collaborative work in A/E/C projects: A ten-year review , 2012 .

[27]  David Gurley,et al.  Practical Knowledge Builds Projects: Case for Independent Construction Information Management , 1998 .

[28]  Chimay J. Anumba,et al.  An integrated framework for concurrent life-cycle design and construction , 1998 .