A modified block replacement policy

A well known preventive replacement policy is the block replacement policy (BRP). In such a policy the item undergoes a planned replacement at a sequence of equally spaced time points independent of failure history. The main advantage of a BRP is its simplicity, because under this policy it is unnecessary to keep detailed records about times of failures or ages of items. The main drawback of a BRP is that at planned replacement times we may be replacing practically new items. In this paper we study a modified BRP which is free of this drawback. We calculate the expected cost of following a modified BRP for lifetime distributions possessing a special structure and illustrate it for the case of an Erlang distribution. A numerical comparison is made between a modified BRP and a standard BRP for the special case of a two stage Erlang distribution.