Prioritizing and quantifying the risk of outstanding corrective actions
暂无分享,去创建一个
Abstract This paper presents methods for assessing the risk of outstanding corrective actions, and describes how the methods were applied at a nuclear power station. The methods are motivated by a current industry focus on risk-informed operation and a current NRC focus on risk-informed regulation. Application of the methods provides: (1) a risk-informed basis for establishing schedules and allocating resources to implement corrective actions; (2) a risk-informed basis for justifying continued operation until corrective actions are implemented.