Dynamic Group Scheduling Heuristics in a Flow-through Cell Environment*

The increased use of cellular manufacturing configurations designed to grapple with increasing competitive pressures is providing manufacturing managers and engineers with a broad variety of operational challenges. Many questions concerning the best procedures and policies for the day-to-day operation of manufacturing cells are still unanswered. The primary objective of this study is to compare the performance of traditional single-stage heuristics and the two-stage group scheduling heuristics that have exhibited superior performance in previous studies in a flow-through cell environment under a rigorous set of experimental conditions. Such a comparison is of great interest since each previous study has focused on proposing new heuristics and testing them against some particular baseline heuristic, often without comprehensive comparisons to the broad variety of previously proposed heuristics. Two single-stage heuristics and four two-stage heuristics are examined under sixteen experimental conditions (four experimental factors at two levels each). The experimental factors examined are shop load, due date tightness, setup to run-time ratio, and interarrival time distribution. Results vary by experimental condition and performance criteria, but in general, two-stage heuristics outperformed single-stage heuristics under all experimental conditions, as well as being relatively insensitive to changing experimental conditions. In addition, two of the two-stage heuristics displayed superior performance on all performance measures under most experimental conditions. Finally, the results indicated that interarrival time distribution does have a major impact on the performance of scheduling heuristics.

[1]  Charles T. Mosier,et al.  Analysis of group technology scheduling heuristics , 1984 .

[2]  T. J. Greene,et al.  A review of cellular manufacturing assumptions, advantages and design techniques , 1984 .

[3]  Jean-Louis Malouin,et al.  Evaluation of the Shortest Processing Time Scheduling Rule with Truncation Process , 1973 .

[4]  Keith L. McRoberts,et al.  On scheduling in a GT environment , 1982 .

[5]  Barbara B. Flynn Repetitive lots: The use of a sequence-dependent set-up time scheduling procedure in group technology and traditional shops , 1987 .

[6]  Nancy Lea Hyer,et al.  Cellular manufacturing in the U.S. industry: a survey of users , 1989 .

[7]  Don T. Phillips,et al.  A state-of-the-art survey of dispatching rules for manufacturing job shop operations , 1982 .

[8]  C. L. Ang,et al.  A comparative study of the performance of pure and hybrid group technology manufacturing systems using computer simulation techniques , 1984 .

[9]  Farzad Mahmoodi,et al.  A comparison of exhaustive and non-exhaustive group scheduling heuristics in a manufacturing cell , 1991 .

[10]  Douglas A. Elvers,et al.  The Sensitivity of the Relative Effectiveness of Job Shop Dispatching Rules with Respect to Various Arrival Distributions , 1974 .

[11]  F. Robert Jacobs,et al.  Applications and Implementation: AN EXPERIMENTAL COMPARISON OF CELLULAR (GROUP TECHNOLOGY) LAYOUT WITH PROCESS LAYOUT , 1987 .

[12]  Asoo J. Vakharia,et al.  Job and Family Scheduling of a Flow-Line Manufacturing Cell: A Simulation Study , 1991 .

[13]  Larry R. Taube,et al.  The facets of group technology and their impacts on implementation--A state-of-the-art survey , 1985 .

[14]  Farzad Mahmoodi,et al.  An investigation of dynamic group scheduling heuristics in a job shop manufacturing cell , 1990 .

[15]  F. Robert Jacobs,et al.  A simulation comparison of group technology with traditional job shop manufacturing , 1986 .

[16]  F. Robert Jacobs,et al.  REPETITIVE LOTS: FLOW-TIME REDUCTIONS THROUGH SEQUENCING AND DYNAMIC BATCH SIZING , 1988 .