Railway line capacity utilisation and its impact on maintenance costs

Abstract In this paper, we analyse how railway maintenance costs are affected by different levels of railway line capacity utilisation. Previous studies have focused on the wear and tear of the infrastructure, while this paper shows that it is important to also acknowledge the heterogeneity of the maintenance production environment. Specifically, we estimate marginal maintenance costs for traffic using econometric methods on a panel dataset from Sweden and show that these costs increase with line capacity utilisation. The results are significant considering that current EU regulation (2015/909) states that track access charges can be based on marginal costs, with the aim of achieving an efficient use of available infrastructure capacity.

[1]  T. Kloek,et al.  Econometric Methods with Applications in Business and Economics , 2004 .

[2]  Per Olov Lindberg,et al.  Railway Timetabling Using Lagrangian Relaxation , 1998, Transp. Sci..

[3]  Phill Wheat,et al.  Estimating the relative cost of track damage mechanisms: combining economic and engineering approaches , 2017, Proceedings of the Institution of Mechanical Engineers. Part F, Journal of rail and rapid transit.

[4]  Matthias Ehrgott,et al.  Railway track allocation: models and methods , 2011, OR Spectr..

[5]  M. Andersson Marginal Railway Infrastructure Costs in a Dynamic Context , 2007 .

[6]  Per Johansson,et al.  An Economic Analysis of Track Maintenance Costs , 2004 .

[7]  Alexander Pfister,et al.  Estimating Marginal Costs for the Austrian Railway System , 2002 .

[8]  Hans E. Boysen,et al.  General model of railway transportation capacity , 2012 .

[9]  Kristofer Odolinski,et al.  Dynamics in rail infrastructure provision: Maintenance and renewal costs in Sweden , 2018, Economics of Transportation.

[10]  Chris Nash,et al.  Marginal cost and other pricing principles for user charging in transport: a comment , 2003 .

[11]  Mats Andersson,et al.  Rail cost allocation for Europe : Annex 1A. Marginal cost of railway infrastructure wear and tear for freight and passenger trains in Sweden , 2009 .

[12]  Phill Wheat,et al.  D5.3: Access Charge Final Report. The sustainable freight railway: Designing the freight vehicle – track system for higher delivered tonnage with improved availability at reduced cost (SUSTRAIL) , 2015 .

[13]  Tomas Lidén Railway Infrastructure Maintenance - A Survey of Planning Problems and Conducted Research , 2015 .

[14]  Tomas Lidén Survey of railway maintenance activities from a planning perspective and literature review concerning the use of mathematical algorithms for solving such planning and scheduling problems , 2014 .

[15]  W. Greene,et al.  Economies of Scale in U.S. Electric Power Generation , 1976, Journal of Political Economy.

[16]  Phill Wheat,et al.  CATRIN (Cost Allocation of TRansport INfrastructure cost), Deliverable 8 - Rail Cost Allocation for Europe , 2009 .

[17]  David Roodman,et al.  A Note on the Theme of Too Many Instruments , 2008 .

[18]  Mats Andersson,et al.  Estimating the marginal cost of railway track renewals using corner solution models , 2012 .

[19]  R. Blundell,et al.  Initial Conditions and Moment Restrictions in Dynamic Panel Data Models , 1998 .

[20]  Gunilla Björklund,et al.  Marginal railway track renewal costs: a survival data approach , 2016 .

[21]  F. Windmeijer A Finite Sample Correction for the Variance of Linear Two-Step GMM Estimators , 2000 .

[22]  Evert Andersson,et al.  Track-friendly Bogies for High Speeds and Heavy Payloads , 1989 .

[23]  Bo-Lennart Nelldal,et al.  Kapacitetsanalys av järnvägsnätet i Sverige : Delrapport 1, Hur många tåg kan man köra? En analys av teoretisk och praktisk kapacitet , 2009 .

[24]  Kristofer Odolinski,et al.  The impact of axle loads on rail infrastructure maintenance costs , 2016 .

[25]  M. Arellano,et al.  Another look at the instrumental variable estimation of error-components models , 1995 .

[26]  Jan-Eric Nilsson,et al.  Tidtabelläggning : principer, tumregler och utfall , 2015 .

[27]  Jan-Eric Nilsson,et al.  Towards a welfare enhancing process to manage railway infrastructure access , 2002 .

[28]  Phill Wheat,et al.  Assessing the Marginal Infrastructure Maintenance Wear and Tear Costs for Britain's Railway Network , 2008 .

[29]  Jan-Eric Nilsson,et al.  Estimating the marginal maintenance cost of rail infrastructure usage in Sweden : does more data make a difference? , 2017 .

[30]  Per Olov Lindberg,et al.  Optimering och tidtabelläggning : slutrapportering av förstudie , 2017 .

[31]  Kristofer Odolinski,et al.  Assessing the cost impact of competitive tendering in rail infrastructure maintenance services : evidence from the Swedish Reforms (1999 to 2011) , 2016 .

[32]  Tomas Lidén,et al.  Towards concurrent planning of railway maintenance and train services , 2016 .

[33]  W. Newey,et al.  Estimating vector autoregressions with panel data , 1988 .

[34]  Adam Beagles SHEFFIELD The sustainable freight railway: Designing the freight vehicle – track system for higher delivered tonnage with improved availability at reduced cost SUSTRAIL , 2012 .

[35]  Hans Boysen,et al.  Quicker meets, heavier loads and faster empties : Effects on transportation capacity and cycle time , 2013 .

[36]  Werner Rothengatter,et al.  How good is first best? Marginal cost and other pricing principles for user charging in transport , 2003 .

[37]  Anders Lindfeldt Kapacitetsutnyttjande i det svenska järnvägsnätet : Uppdatering och analys av utvecklingen 2008 – 2012 , 2014 .

[38]  Martin Joborn,et al.  Dimensioning windows for railway infrastructure maintenance: Cost efficiency versus traffic impact , 2016, J. Rail Transp. Plan. Manag..

[39]  Anders Lindfeldt,et al.  Railway capacity analysis: methods for simulation and evaluation of timetables, delays and infrastructure , 2015 .