A heuristic algorithm for the m-machine, n-job flow-shop sequencing problem

In a general flow-shop situation, where all the jobs must pass through all the machines in the same order, certain heuristic algorithms propose that the jobs with higher total process time should be given higher priority than the jobs with less total process time. Based on this premise, a simple algorithm is presented in this paper, which produces very good sequences in comparison with existing heuristics. The results of the proposed algorithm have been compared with the results from 15 other algorithms in an independent study by Park [13], who shows that the proposed algorithm performs especially well on large flow-shop problems in both the static and dynamic sequencing environments.