A TYPE-2 FUZZY OPTIMIZATION MODEL FOR PROJECT PORTFOLIO SELECTION AND SCHEDULING INCORPORATING PROJECT INTERDEPENDENCY AND SPLITTING

This paper presents a new optimization model and a new interval type-2 fuzzy solution approach for project portfolio selection and scheduling (PPSS) problem, in which split of projects and re-execution are allowable. Afterward, the approach is realized as a multi-objective optimization that maximizes total benefits of projects concerning economic concepts by considering the interest rate and time value of money and minimizes the tardiness value and total number of interruptions of chosen projects. Besides, budget and resources limitation, newfound relations are proposed to consider dependency relationships via a synergy among projects to solve PPSS problem hiring interval type-2 fuzzy sets. For validation of the model, numerical instances are provided and solved by a new extended procedure based on fuzzy optimistic and pessimistic viewpoints regarding several situations. In the end, their results are studied. The results show that it is more beneficial when projects are allowed to be split.

[1]  T. T. Narendran,et al.  A model for new product introduction under resource constraints and product interdependence , 2016 .

[2]  Tamás Kis,et al.  Allocating raw materials to competing projects , 2020, Comput. Ind. Eng..

[3]  Shu-Hsien Liao,et al.  Investment project valuation based on a fuzzy binomial approach , 2010, Inf. Sci..

[4]  S. M. Mousavi,et al.  SUSTAINABLE INFRASTRUCTURE PROJECT SELECTION BY A NEW GROUP DECISION-MAKING FRAMEWORK INTRODUCING MORAS METHOD IN AN INTERVAL TYPE 2 FUZZY ENVIRONMENT , 2019, International Journal of Strategic Property Management.

[5]  Manoj Kumar Tiwari,et al.  Project portfolio selection and scheduling optimization based on risk measure: a conditional value at risk approach , 2019, Annals of Operations Research.

[6]  S. Meysam Mousavi,et al.  A New Optimization Model for Project Portfolio Selection Under Interval-Valued Fuzzy Environment , 2015 .

[7]  Melvyn Sim,et al.  Managing Underperformance Risk in Project Portfolio Selection , 2015, Oper. Res..

[8]  S. Meysam Mousavi,et al.  A new soft computing model based on linear assignment and linear programming technique for multidimensional analysis of preference with interval type-2 fuzzy sets , 2019, Appl. Soft Comput..

[9]  Jerry M. Mendel,et al.  Interval Type-2 Fuzzy Logic Systems Made Simple , 2006, IEEE Transactions on Fuzzy Systems.

[10]  S. Meysam Mousavi,et al.  A new interval type-2 fuzzy approach for analyzing and monitoring the performance of megaprojects based on earned value analysis (with a case study) , 2019, Neural Computing and Applications.

[11]  H. Baker,et al.  Capital budgeting valuation : financial analysis for today's investment projects , 2011 .

[12]  Karel Skokan Technological and Economic Development of Economy , 2011 .

[13]  Manoranjan Maiti,et al.  A method to solve linear programming problem with interval type-2 fuzzy parameters , 2018, Fuzzy Optimization and Decision Making.

[14]  Radhika Santhanam,et al.  A DECISION MODEL FOR INTERDEPENDENT INFORMATION SYSTEM PROJECT SELECTION , 1996 .

[15]  P. Schonfeld,et al.  Selection and Scheduling of Interdependent Transportation Projects with Island Models , 2006 .

[16]  Ali Asghar Tofighian,et al.  Modeling and solving the project selection and scheduling , 2015, Comput. Ind. Eng..

[17]  Irem Ozkarahan,et al.  A supply chain distribution network design model: An interactive fuzzy goal programming-based solution approach , 2008 .

[18]  Yuejin Tan,et al.  Project portfolio selection and scheduling under a fuzzy environment , 2019, Memetic Comput..

[19]  Vahid Mohagheghi,et al.  A NEW ANALYTICAL METHODOLOGY TO HANDLE TIME-COST TRADE-OFF PROBLEM WITH CONSIDERING QUALITY LOSS COST UNDER INTERVAL-VALUED FUZZY UNCERTAINTY , 2019, Technological and Economic Development of Economy.

[20]  Shu-Cherng Fang,et al.  An extended model for project portfolio selection with project divisibility and interdependency , 2016 .

[21]  Shu-Shun Liu,et al.  Optimizing project selection and scheduling problems with time-dependent resource constraints , 2011 .

[22]  Jürgen Zimmermann,et al.  A branch-and-bound procedure for the resource-constrained project scheduling problem with partially renewable resources and general temporal constraints , 2020, OR Spectr..

[23]  S. Meysam Mousavi,et al.  Evaluating large, high-technology project portfolios using a novel interval-valued Pythagorean fuzzy set framework: An automated crane project case study , 2020, Expert Syst. Appl..

[24]  Michael J. Ryan,et al.  Memetic algorithm for solving resource constrained project scheduling problems , 2020, Automation in Construction.

[25]  Xiaoxia Huang,et al.  Project selection and scheduling with uncertain net income and investment cost , 2014, Appl. Math. Comput..

[26]  Ahti Salo,et al.  Robust portfolio modeling with incomplete cost information and project interdependencies , 2008, Eur. J. Oper. Res..

[27]  S. Meysam Mousavi,et al.  A new interval type-2 fuzzy approach for multi-scenario project cash flow assessment based on alternative queuing method and dependency structure matrix with a case study , 2020, Eng. Appl. Artif. Intell..

[29]  Xindong PENG,et al.  FUZZY DECISION MAKING METHOD BASED ON COCOSO WITH CRITIC FOR FINANCIAL RISK EVALUATION , 2020 .

[30]  Norman R. Baker,et al.  Economic Models for R and D Project Selection in the Presence of Project Interactions , 1984 .

[31]  S. Meysam Mousavi,et al.  Determining project characteristics and critical path by a new approach based on modified NWRT method and risk assessment under an interval type-2 fuzzy environment , 2018 .

[32]  Mir-Bahador Aryanezhad,et al.  A modular Decision Support System for optimum investment selection in presence of uncertainty: Combination of fuzzy mathematical programming and fuzzy rule based system , 2011, Expert Syst. Appl..

[33]  Ali Shafahi,et al.  A Linearization Approach for Project Selection with Interdependencies in Resource Costs , 2013, ICORES.

[34]  Maciek Nowak,et al.  A trade-off multiobjective dynamic programming procedure and its application to project portfolio selection , 2021, Ann. Oper. Res..

[35]  Ye Tian,et al.  Expanded model of the project portfolio selection problem with divisibility, time profile factors and cardinality constraints , 2015, J. Oper. Res. Soc..

[36]  Juite Wang,et al.  A fuzzy set approach for R&D portfolio selection using a real options valuation model , 2007 .

[37]  Ronald G. Askin,et al.  Project selection, scheduling and resource allocation with time dependent returns , 2009, Eur. J. Oper. Res..

[38]  Hassan Mishmast Nehi,et al.  A Solving Method for Fuzzy Linear Programming Problem with Interval Type-2 Fuzzy Numbers , 2019, International Journal of Fuzzy Systems.

[39]  Pankaj Kumar,et al.  Fuzzy R&D portfolio selection of interdependent projects , 2011, Comput. Math. Appl..