Standardization of highway construction delay claim analysis--a highway bridge case study

Highway construction efficiency is critical to highway users such as the trucking industry given today’s era of shortages in funding, and given the need for major re-investments in the highway system. One topic that can add to project costs relates to delays and how contractors are reimbursed for such delays. Delays are common in construction, especially in complex heavy highway and other infrastructure projects, and the claims they generate have negative effects on project schedules and costs. In spite of this, the analysis of claims is hindered due to the variety of methods and analysis techniques in use and lack of standardization in the incorporation of delay claim analysis methods in construction contracts. This paper reviews different methods for delay claim analysis and outlines their advantages and disadvantages. A case study of a bridge project is used to demonstrate the potential for manipulation by using different methods for the same delay case. The analysis shows clearly that a standardized process for delay claim analysis would improve highway construction contracting. Research needs to create a standardized process are outlined.

[1]  Construction Contract Damages: A Critical Analysis of the "Total Cost" Method of Valuing Damages for "Extra Work" , 2003 .

[2]  James E. Diekmann,et al.  Concurrent delays in construction projects , 1987 .

[3]  Aminah Robinson Fayek,et al.  Fuzzy Logic Approach for Activity Delay Analysis and Schedule Updating , 2005 .

[4]  Robert Frank Cushman,et al.  Proving and Pricing Construction Claims , 1990 .

[5]  Sabah Alkass,et al.  Construction delay analysis techniques , 1996 .

[6]  Sabah Alkass,et al.  Computer aided construction delay analysis and claims preparation , 1995 .

[7]  C. William Ibbs,et al.  PROJECT CHANGE MANAGEMENT SYSTEM , 2001 .

[8]  David Arditi,et al.  Construction Delay Computation Method , 2001 .

[9]  Long D. Nguyen The dynamics of float, logic, resource allocation, and delay timing in forensic schedule analysis and construction delay claims , 2007 .

[10]  David Arditi,et al.  Selecting a delay analysis method in resolving construction claims , 2006 .

[11]  Vera A. Lovejoy Claims schedule development and analysis: Collapsed as-built scheduling for beginners , 2004 .

[12]  REGINALD M. JONES,et al.  Lost Productivity : Claims for the Cumulative Impact of Multiple Change Orders , 2001 .

[13]  Simaan M. AbouRizk,et al.  Analysis of Productivity on a Tunnel Operation Using Computer Simulation , 1997 .

[14]  William Ibbs,et al.  Alternative for Quantifying Field-Overhead Damages , 2007 .

[15]  Gasan G. Kallo Legal Issues: Estimating Loss of Productivity Claims , 1996 .

[16]  William Schwartzkopf,et al.  Calculating Lost Labor Productivity in Construction Claims , 1995 .

[17]  Matthew James Lankenau Owner caused delay: Field overhead damages , 2003 .

[18]  Jon M. Wickwire,et al.  Construction Scheduling: Preparation, Liability, and Claims , 1991 .

[19]  M. Haseeb,et al.  PROBLEMS OF PROJECTS AND EFFECTS OF DELAYS IN THE CONSTRUCTION INDUSTRY OF PAKISTAN , 2012, Australian Journal of Business and Management Research.

[20]  James G. Zack,et al.  DELAY AND DELAY ANALYSIS: ISN'T IT SIMPLE ? , 2006 .

[21]  William Ibbs,et al.  Schedule Analysis under the Effect of Resource Allocation , 2007 .

[22]  Awad S. Hanna,et al.  Quantitative Definition of Projects Impacted by Change Orders , 2002 .

[23]  Chabota Kaliba,et al.  Cost escalation and schedule delays in road construction projects in Zambia , 2009 .

[24]  Seulkee Lee,et al.  Understanding and quantifying the impact of changes on construction labor productivity: Integration of productivity factors and quantification methods , 2007 .

[25]  Mohammad Najafi,et al.  Productivity Study of Microtunneling Pipe Installation Using Simulation , 2007 .

[26]  William Ibbs,et al.  FLORA: New Forensic Schedule Analysis Technique , 2008 .

[27]  Ralph D. Ellis,et al.  THE ROOT CAUSES OF DELAYS IN HIGHWAY CONSTRUCTION , 2003 .

[28]  Frank F Saccomanno,et al.  Modified but-for method for delay analysis , 2005 .

[29]  Tarek Hegazy,et al.  Daily Windows Delay Analysis , 2005 .

[30]  Brian E. Kasen,et al.  FEATURE: Thinking Ahead with Forward Pricing , 1996 .

[31]  Awad S. Hanna,et al.  STATISTICAL-FUZZY APPROACH TO QUANTIFY CUMULATIVE IMPACT OF CHANGE ORDERS , 2002 .

[32]  Sadi Assaf,et al.  Causes of delay in large construction projects , 2006 .

[33]  Michael R. Finke A Better Way to Estimate and Mitigate Disruption , 1998 .

[34]  Richard Smith,et al.  ESTIMATING LOST LABOR PRODUCTIVITY IN CONSTRUCTION CLAIMS TCM Framework: 6.4 - Forensic Performance Assessment , 2004 .

[35]  A. R. George,et al.  Schedule Delay Analysis , 2016 .

[36]  Simaan M. AbouRizk,et al.  Application of Computer Simulation in Resolving Construction Disputes , 1993 .

[37]  Saied Kartam Generic Methodology for Analyzing Delay Claims , 1999 .

[38]  William Schwartzkopf,et al.  Calculating Construction Damages , 1992 .

[39]  G. O. Jagboro,et al.  The effects of construction delays on project delivery in Nigerian construction industry , 2002 .

[40]  H R Thomas SCHEDULE ACCELERATION, WORK FLOW, AND LABOR PRODUCTIVITY , 2000 .

[41]  Boyd C. Paulson,et al.  Professional Construction Management , 1978 .