08: Projektmanagement im Zeitalter der Digitalisierung, WS 2018/19, 03.12.2018
暂无分享,去创建一个
08 |
0:00:00 Start
0:00:14 Session 8
0:01:27 Project Planning : Schedule Management Plan
0:19:06 Schedule Creation / Planning level of detail
0:26:00 Schedule Creation / Planning level of detail / example
0:29:18 Schedule Creation / Planning / Sources of uncertainty
0:39:36 Schedule Creation / Planning / Estimation
0:47:26 Schedule Creation / Planning / Estimation / Success factors
0:53:17 Planning Poker / Estimation method
0:55:14 Schedule Creation / Planning / Estimation of Duration / Things to consider
1:04:26 Schedule Creation / Planning / Estimation of Duration / Productivity
1:10:35 Schedule Creation / Planning / Estimation of Duration / OEE Example
1:14:08 Schedule Creation / Planning / Estimation of Duration / Solution Strategy
1:19:32 Schedule Creation / Planning / Productivity